Milestone Tracker — the first rows of the actual spreadsheet

Projects template

Milestone Tracker

Baseline against forecast, showing slippage in days per milestone.

Live formulas
11
Columns
6
File
8 KB

$5

Checkout opening soon

Or get it with all 66 paid templates in the complete pack — $45.

Works in Excel 2013 and later, Microsoft 365, Google Sheets and LibreOffice Calc. Set up to print on one page wide.

About this Milestone Tracker template

Projects slip one milestone at a time, and it is easy to miss until the end date moves. This Excel milestone tracker records the baseline date you committed to and the current forecast date for every milestone, and works out the slippage in days.

The schedule health summary shows milestones complete, total and worst slippage, how many milestones are slipping and the next one due.

Good for

  • Reporting schedule progress to a project board
  • Spotting early slippage before it hits the end date
  • Tracking key dates on a long programme

What it works out for you

Schedule health

  • Milestones complete
  • Total slippage (days)
  • Worst slippage
  • Milestones slipping
  • Next milestone due

What you fill in

The table has 6 columns. Calculated columns fill themselves in; the rest are yours to type over.

  • Milestone
  • Owner
  • Baseline date
  • Forecast date
  • Slippage (days)
  • Status

How to use it

Baseline is the date you originally committed to. Slippage compares forecast against it, so the damage is visible early.

The file opens with sample rows so you can see every formula working before you change anything. Type your own figures over them. When you need more rows, insert them inside the existing block rather than underneath it, so the totals keep covering every row.

Functions it uses

Every one of these exists in Excel, Google Sheets and LibreOffice, so the file behaves the same wherever you open it.

COUNTIFIFIFERRORMAXMINSUMTEXT

Questions about the Milestone Tracker

What is a baseline date?

The date you originally agreed for the milestone. It should not change once set, so slippage is always measured against the original commitment.

How is slippage calculated?

Forecast date minus baseline date, in days. A positive number means the milestone is running late.

What should I change when a milestone slips?

Update the forecast date and leave the baseline alone, so the tracker keeps showing the true slippage.

More projects templates